Max Korzh, National Arena 2026
Stadium rigging: 98 points and delay towers
Case study
- 98rigging points
- 435 kNtotal suspended load
- 9.5 kNmax per point
- 17.7 mmax trim height
The challenge
A stadium concert with the main stage, screens and sound hung from 98 points, plus delay towers on the pitch, all laid over the stadium plan before the build.
What we did
The rigging design: the load suspension plots and their overlay with the stage and the delay towers, BIM modelling of the supplier's custom parts, the layout and the structural verification file, plus the survey and the setting-out of the ground support on the pitch.
The result
The concert took place on 23 May 2026 at the National Arena.